The first Steering Committee (SC) reviewing the progress of the project in the first 3 months of execution and discussing the programme for next 6 months (12 April till 11 October 2015) took place on the 28th April of 2015 in Skopje with presence of the Spanish, Dutch and BC Project Leaders, representative of FIIAPP; InfoMil; CFCD; Ministry of Environment and Physical Planning, EU Delegation; Secretariat for European Affairs and Project team. At the beginning the Macedonian Project Leader emphasized the importance of the project for the State Environmental Inspectorate and his expectation of good support from all stakeholders. Rules of Procedures of the SC were adopted.
During the meeting Quarterly Report 1; Operative Side Letter 2; Addendum 1 and Inception Report were presented by the RTA. General project progress was assessed highly positively. Main outputs were listed: SEI website & visibility materials; institutional assessment; translation of Law on Inspection Supervision; translation of parts of existing legislation relevant to environmental inspection, and delivery of the draft Addendum 1 after discussion with EC, EU Delegation & CFCD representatives, to, among other issues, extend the duration of the project for 7 additional months. Brief presentation of Basecamp as a very useful online tool for the management of the project and the access to project-related documents was done by RTA.
Related documents:
Agenda.doc
Presentation_First St_Committee_Twinning_Inspection_April_2015.pptx
Rules of Procedure_Twinning Inspection.pdf